Choose the supply boundary
IEC 62208:2023 addresses the enclosure before the assembly manufacturer incorporates switchgear and controlgear. Specify the empty cabinet’s dimensions, material, mounting arrangements and protection requirements. Identify whether plates, rails, gland plates and plinths are included.
Define the completed assembly
IEC 61439-1:2020 provides general requirements used with the applicable product part of the series. A completed-board enquiry needs the electrical ratings, equipment arrangement and verification responsibilities as well as the enclosure schedule. Allocate temperature-rise and short-circuit verification to the responsible assembly manufacturer.
Make the two offers comparable
State who supplies and fits equipment, makes cable openings, wires the board and completes verification. An empty-enclosure declaration cannot establish the performance of the populated assembly. Ask each bidder to identify its delivery boundary and handover documents on the same schedule.
Release the coordinated package
Issue the single-line diagram and approved arrangement with the enquiry. Agree mounting plates, gland plates, plinths, internal separation where required and site interfaces before production. The acceptance plan should name the responsible reviewer for the completed configuration.
Further reading & sources
General procurement guidance. Confirm project-specific requirements with the responsible design team and the supplier.
Use this on your project
Download the requirements and delivery templates or record a comparison against your specification.