Start with the correct approval object
IEC 62208:2023 addresses empty enclosures before switchgear and controlgear are installed. Its scope covers enclosures for assemblies up to 1,000 V AC or 1,500 V DC in general indoor or outdoor use. The 2023 edition replaces the 2011 edition. Put the required edition and the exact enclosure configuration in the enquiry.
Make the submittal useful
Ask for the model number, dimensional drawing, material and finish, ingress and impact requirements, and the declaration or test-report reference supporting the offer. A short schedule linking each requirement to a document is easier to assess than a collection of brochures. Include the accessories and permitted modifications in that schedule.
Define the completed panel scope
The panel builder’s responsibility extends beyond supplying the empty cabinet. Agree the applicable assembly requirements, design inputs and verification documents for the installed equipment. Specify any project requirements for marine service, hazardous locations, seismic performance or electromagnetic compatibility separately.
Release a buildable package
Before manufacture, coordinate component layout, heat loss, cable entries, mounting and access. Allocate factory, panel-shop and site modifications explicitly, with responsibility for the resulting enclosure performance. Share your specification and required quantities to discuss suitable enclosure and supply options.
Further reading & sources
General procurement guidance. Confirm project-specific requirements with the responsible design team and the supplier.
Use this on your project
Download the requirements and delivery templates or record a comparison against your specification.